Business

Nexans Makes Final Cable Delivery to Canada’s Strait of Belle Isle Subsea HVDC Power Link

May 14, 2018
Subsea HVDC Cable

Subsea HVDC Cable

  • Nexans has successfully completed the delivery of the Strait of Belle Isle power link, which is part of the Lower Churchill project in Eastern Canada.
  • The six-year project to create a 350 kV power link across the Strait of Belle Isle has been completed with the delivery of the spare length of cable.

Paris La Défense, May 14, 2018 - Nexans has completed a six-year project to design, manufacture, supply and install approximately 100 km of subsea high voltage direct current (HVDC) cable and accessories for Nalcor Energy’s Strait of Belle Isle Marine Cable Crossing in Newfoundland and Labrador, Canada. The project, which now connects Labrador with the island of Newfoundland, reached its conclusion when Nexans delivered the final 2.3 km length of cable that will provide a spare ready for use.

6 years

duration of the Lower Churchill project

100 km

of subsea HVDC cable supplied and installed by Nexans

350 kV

capacity of the cables supplied by Nexans

110 m

depth of water at which the cables are installed

A masterwork of engineering and installation

The 350 kV HVDC cables used for the project are based on Nexans’ well-proven mass-impregnated design. They include three lengths of submarine cables with an integrated fiber-optic element together with underground cables that were used for the land connections at either side of the strait. The accessories comprise joints, spares and terminations. The subsea cables were installed in water depths of up to 110 m by Nexans’ own installation vessel, the C/S Nexans Skagerrak.

 

“ The Strait of Belle Isle project was a major operation that called on our highly skilled people in a wide range of areas and especially the marine and onshore installation. One of our greatest challenges in this remote area was the sea ice as well as dense fog and cold weather. It is a tribute to Nexans’ engineering and installation capability that the project has been completed safely and successfully. ”

Peggy Aasheim

Nexans project manager for the Strait of Belle Isle

The spare cable is being stored on a spool held on the Corner Brook waterfront on the west coast of the island of Newfoundland.

The Strait of Belle Isle Marine Cable Crossing is a key element in the overall Lower Churchill Project, which includes construction of an 824 MW hydroelectric generating facility and more than 1,600 km of transmission lines across the province.

The 350 kV HVDC cables were manufactured by Nippon High Voltage Cable Corporation (NVC), Nexans’ facility in Tokyo, Japan.

Your Contact

Barry Zeidenberg

North America Marketing Communications

Contact us

Topics on which you wish to get more informations:

Required fields*

Please check your entry and try again.

An email address must contain a single @

Personal data protector

You have the right to object to the processing of your personal data and/or their use for direct marketing or commercial purposes

Thank you!

Thanks for contacting us. We will be in touch with you shortly.

Error

An error occurred. Please try again.

Close